A simple date addition ignores closures
A2+B2 counts calendar days. It does not use the supplied mask and closure dates.
Step-by-step guide · read-only ·
Loading your interactive spreadsheet…
Preparing the worksheet and formulas…
Fill C2:C5 with each date reached after the working-day offset in column B, starting from column A. Use the Monday-first text weekend mask in G2 and the closure dates in G4:G7. Do not count the starting date when moving; a zero offset returns that original date even when it is closed.
Follow the highlighted cells. Switch to Your turn to edit. Answer cells: C2, C3, C4, C5. Browser calculations may differ from your Excel version.
Practice stays on this device. No worksheet data is uploaded.
Move forward or backward by working days, with a configurable weekend and a separate office-closure list.
WORKDAY.INTL advances by eligible working dates. The weekday mask and closure list remain fixed as the start and offset move down each row.
=WORKDAY.INTL(A2,B2,$G$2,$G$4:$G$7)The formula uses the interactive worksheet above. Adjust ranges and criteria for your own data.
Adding 1 to a date always advances one calendar day. Advancing one working day can skip several closed dates. The starting date is excluded for a nonzero offset.
Use whole numeric date serials from 2000-01-01 through 2099-12-31, whole offsets from -366 through 366, a seven-character text mask with at least one working weekday, and up to four whole numeric closure dates or blank cells. Text dates, time fractions and booleans remain ungraded.
Column A holds numeric dates displayed as dates, not date strings. A start on a closed day is allowed.
Positive offsets move forward and negative offsets move backward. A zero offset returns the start unchanged; it is not a request to find the next open date.
G2 is seven text characters: 0 means working and 1 means closed, starting with Monday. 0000110 closes Friday and Saturday.
Dates in G4:G7 close otherwise eligible days. A repeated closure or one already on a weekend does not close an extra day. These are invented office closures, not a national calendar.
Fill C2 down through C5. Both calendar references stay absolute; the source row moves. Then compare the alternative weekday patterns and leap-year cases.
A2+B2 counts calendar days. It does not use the supplied mask and closure dates.
Keep the mask and holiday range absolute. Only the start-date and offset rows should move.
A zero working-day offset preserves its starting date, including a weekend or closure.
Formula entry, filling, all authored datasets, walkthrough controls and original/current/frozen downloads were checked in Chrome on October 17, 2026. Native Mac Excel also calculated all 24 answers across the six supplied datasets from an uncached workbook copy. Native source editing and save/reopen compatibility, and Google Sheets recalculation, remain unverified. Dates are numeric Excel 1900-system serials; closures are invented office-calendar examples.
Content version 1. Practice checks compare calculated results across different datasets; they do not certify every possible formula.